TM 9-2320-440-13&P
0154-2
0154
CLEANING/INSPECTION
1.
Clean all metal parts with solvent cleaning compound.
2.
Clean equalizing beam bores with emery cloth or cylinder hone to remove all corrosion.
3.
Inspect equalizing beam for cracks and damage.
4.
Replace equalizing beam if cracked or damaged.
END OF TASK
EQUALIZING BEAM BUSHING INSTALLATION
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
NOTE
Bushings are installed on both equalizing beams the same way.
Right equalizing beam
shown.
1.
Lubricate end bushing (1) and center bushing (3) with soap solution.
WARNING
Use of press of 10,000 lbs (4,540 kg) capacity or greater is required to remove or
install bushings on equalizer beams.
Use care when pressing bushings to prevent
injury or death to personnel.
Always wear eye protection to prevent injury when
operating press.
2.
Press center bushing (3) into equalizing beam (2) so center bushing (3) extends equally from both sides of
equalizing beam (2).
3.
Press end bushing (1) into equalizing beam (2) so end bushing (1) extends equally from both sides of
equalizing beam (2).
END OF TASK
THAAD0370


Back to Top