0014-7
TM 9-2330-335-14&P
0014
13
(Con’t)
Before
Radial Tires
and Wheels
e. Re-torque wheel nuts at first 100, 500,
1,000 miles (161, 805, 1,609 km), and
every 6,000 miles (9,656 km) thereafter
unless wheel is changed out. Then use
re-torque schedule. Notify Organizational
Maintenance (WP 0097).
Wheel nuts are loose or missing.
Wheel nuts not torqued.
14
Before
Spare Tire
Carrier
WARNING
Spare tire and wheel assembly
weighs 179 lb (81.2 kg). This
requires two people to remove the
spare from the carrier or install it
on the carrier. Slide the spare from
the carrier or onto the carrier.
Refrain from lifting the spare into
position. Failure to comply could
result in injury to personnel.
NOTE
When layed in carrier, convex side
should be in the up position (stud
holes up).
Inspect spare tire carrier assembly for
worn, loose, or missing securing
hardware and cracked/broken welds.
Worn, loose, or missing hardware
and cracked/broken welds are
found.
15
Before
Hubcaps and
HUBODOME
TER®
CAUTION
Do not stand on HUBODOME-
TER®. Doing so could result in
damage to equipment.
a. Inspect hubcaps for damage, loose or
missing hardware, and leakage.
Hubcap is leaking grease or
hardware is loose or missing.
b. Inspect HUBODOMETER® for
missing hardware, damage, and loose
mounting bracket or gage.
Hardware is loose or missing.
Table 1. Operator Preventive Maintenance Checks and Services (PMCS) - Continued.
ITEM
NO.
INTERVAL
MAN-
HOURS
LOCATION
ITEM TO
CHECK/
SERVICE
PROCEDURE
NOT FULLY MISSION
CAPABLE IF:


Back to Top