TM-9-2330-335-14-P

SEMITRAILER, TACTICAL, BREAKBULK/CONTAINER TRANSPORTER, 22-1/2 TON, RESET M871R, M871A1R AND M871A2R

TECHNICAL MANUAL; FIELD AND SUSTAINMENT MAINTENANCE MANUAL (INCLUDES REPAIR PARTS AND SPECIAL TOOLS LIST)

SEPTEMBER 2008

  TM-9-2330-335-14-P - Page 179 of 640

0031-3/(4 blank)
TM 9-2330-335-14&P
0031
INSTALLATION
00031
1.
Install lubrication fitting (Figure 1, Item 14) on retainer bushing (Figure 1, Item 15).
2.
Lube zerk fittings (see WP 0067).
3.
Install retainer bushing (18), bushing bracket (Figure 1, Item 17), two new O-rings (Figure 1, Item 16), and retainer
bushing (Figure 1, Item 15) onto S-camshaft (Figure 1, Item 1) with four new lockwashers (Figure 1, Item 12), washers
(Figure 1, Item 13), and screws (Figure 1, Item 11).
4.
Install bushing retainer (Figure 1, Item 4) and four screws (Figure 1, Item 5).
5.
Lightly lube S-camshaft lobes with GAA grease. Wipe off excess grease.
6.
Install S-camshaft (Figure 1, Item 1) with washer (Figure 1, Item 2), two washers (Figure 1, Item 3), washer
(Figure 1, Item 6), spacer (Figure 1, Item 10), and washer (Figure 1, Item 9).
7.
Install S-camshaft (Figure 1, Item 1), snap ring (Figure 1, Item 7), and new retaining ring (Figure 1, Item 8).
END OF TASK
FOLLOW -ON TASKS
00031
1.
Install brake shoes (WP 0032).
2.
Install brake drum (WP 0033).
3.
Install tire and wheel (WP 0021).
4.
Remove jack stands from axles.
5.
Connect semitrailer to prime mover.
6.
Road test to check for safe operation.
END OF TASK
END OF WORK PACKAGE


Back to Top