MWO-5-2350-262-35-4

ARMORED COMBAT EARTHMOVER (ACE), M9

MODIFICATION WORK ORDER

  MWO-5-2350-262-35-4 - Page 123 of 207

MWO 5--2350--262--35--4
4--20
SECTION III INSTALLATION OF NEW FORWARD RIGHT MANIFOLD
ASSEMBLY -- CONTINUED
4--10 INTERCONNECTION OF NEW FORWARD RIGHT MANIFOLD ASSEMBLY
NOTE
Steps a and b below apply to Figure 4--11 and Table 4--2.
a.
Locate hydraulic hoses identified in following procedures, change hose band markers as applicable, and
connect to new forward right manifold assembly ports as indicated in Figure 4--11 and Table 4--2.
b.
Where applicable, replace identification and destination tags (band markers) attached to existing
hydraulic hoses re--routed and/or relocated as part of modification. Band markers are contained in
Underside Band Marker Kit, 12496969.
Figure 4--11. Identification of Forward Right Manifold Assembly ports