TM 9-2320-209-20-3-4
Section III.
POWER TAKEOFF CONTROLS AND LINKAGE
19-25. TRANSMISSION POWER TAKEOFF SHIFT LINKAGE REMOVAL, REPLACEMENT,
CHECKOUT AND ADJUSTMENT.
TOOLS:
Pliers
5/8-inch wrench
3/4-inch wrench
SUPPLIES:
None
PERSONNEL: One
EQUIPMENT CONDITION:
Truck parked, engine off, handbrake set.
a. Preliminary Procedure.
Remove air hydraulic shield. Refer to Part 2, para
13-14.
b. Removal.
FRAME 1
1.
Pull and turn poppet (1) on yoke end (2) of clevis (3).
2.
Take off yoke end (2) from transmission power takeoff shifter shaft (4).
3.
Using 5/8-inch wrench, unscrew and take out two screws and lockwashers (5),
holding power takeoff shifting lever support (6) to master cylinder (7).
4.
Take off transmission power takeoff shift linkage.
END OF TASK
19-129