INSTALLATION
NOTE
Ensure pitman arm and steering gear shaft alignment marks match.
1.
Install pitman arm (Figure 2, Item 7) on steering gear shaft (Figure 2, Item 2) and drag link (Figure 2, Item 4).
2.
Install pitman arm (Figure 2, Item 7) on steering gear shaft (Figure 2, Item 2) with screw (Figure 2, Item 1) and
locknut (Figure 2, Item 3).
3.
Install pitman arm (Figure 2, Item 7) on drag link (Figure 2, Item 4) with slotted nut (Figure 2, Item 5). Tighten
slotted nut 140 lb-ft (190 N·m).
4.
Install cotter pin (Figure 2, Item 6) on slotted nut (Figure 2, Item 5) and drag link (Figure 2, Item 4).
M5026DAA
7
2
4
6
1
3
5
Figure 2.
Pitman Arm Installation.
END OF TASK
END OF WORK PACKAGE