INSTALLATION - Continued
NOTE
Perform Step (7) if bracket was removed.
7.
Install bracket (Figure 4, Item 8) on PTO (Figure 4, Item 10) with two screws (Figure 4, Item 3).
8.
Install cable pin (Figure 4, Item 1) on PTO control cable (Figure 4, Item 7). Tighten nut (Figure 4, Item 2) against
cable pin.
9.
Install PTO control cable (Figure 4, Item 7) on select lever (Figure 4, Item 13) with washer (Figure 4, Item 12)
and cotter pin (Figure 4, Item 11).
10.
Install spacer (Figure 4, Item 4) and PTO control cable (Figure 4, Item 7) on bracket (Figure 4, Item 8) with
clamp (Figure 4, Item 5), two screws (Figure 4, Item 6), and locknuts (Figure 4, Item 9).
M9791DAA
6
7
8
9
10
11
12
13
5
4
3
2
1
Figure 4.
Transmission PTO Control Cable Installation (M939A2).
END OF TASK
FOLLOW-ON MAINTENANCE
1.
Install exhaust pipe. (Volume 2, WP
0276)
2.
Start engine and check transmission PTO for proper operation. (TM 9-2320-272-10)
END OF TASK
END OF WORK PACKAGE