TEST AND INSPECTION - Continued
12.
Monitor afterglow period as follows:
a.
Push glow plug switch (Figure 6, Item 44) momentarily and wait until wait lamp (Figure 6, Item 41)
flashes. Push starter switch (Figure 6, Item 45), hold for approximately 5 sec, and release. Wait lamp
and glow plug indicator lamps (Figure 6, Item 42) should remain on.
b.
Using stop watch, record time wait lamp (Figure 6, Item 41) remains continuously lit following flashing
of standby period. Proper time is 58 to 62 sec until wait lamp and glow plug indicator lamps
(Figure 6, Item 42) should go out.
13.
If glow plug controller (Figure 6, Item 29) passes Steps 5–7, controller is operational.
47
48
46
45
43
44
42
41
29
MAINT_133
Figure 6.
Glow Plug Controller Check.
END OF TASK