INSPECTION-ACCEPTANCE AND REJECTION CRITERIA
Inspect igniter, nozzle, and air box heater for cracks, pitting, or wear.
END OF TASK
ASSEMBLY
1.
Install nozzle (Figure 2, Item 7) in air box heater (Figure 2, Item 5). Tighten securely.
2.
Install igniter (Figure 2, Item 8) in air box heater (Figure 2, Item 5). Tighten securely.
3.
Install elbow (Figure 2, Item 9) in fuel inlet port of air box heater (Figure 2, Item 5).
4.
Install connector (Figure 2, Item 11) and elbow (Figure 2, Item 10) in air inlet port of air box heater
(Figure 2, Item 5).
END OF TASK
ADJUSTMENT
NOTE
Test igniter and ignition coil simultaneously (WP 0043) and (WP 0044).
Using a thickness gage, adjust igniter-wire air gap to 0.080 inch (2.03 mm) (Figure 3).
0.080 in.
(2.03 mm)
MAINT_138
Figure 3.
Air Box Heater Adjustment.
END OF TASK