(7) After the pump stops operating, repeat leak check in step 4.
(8) Slowly open the OUTLET BLEED valve (4) one turn counterclockwise. Very slowly
open the OUTLET SHUTOFF valve (7) just until you hear gas escaping. Purge the system for ten
minutes; then, close OUTLET SHUTOFF and OUTLET BLEED valve fully clockwise. Close
INLET SHUTOFF valve counterclockwise.
(9) Close the argon gas supply valve (5) fully clockwise. Slowly open the INLET BLEED
valve (1) one turn counterclockwise. Then slowly open (turning counterclockwise) the INLET
SHUTOFF valve (2) sufficiently to relieve high pressure down to 500 psig as read on the INLET
PRESSURE gage (3). Immediately close the INLET SHUTOFF valve (2) and then the INLET.
BLEED valve (1) fully clockwise.
(10) Slowly open the OUTLET BLEED valve (4) one turn counterclockwise. Then,
slowly open (turning counterclockwise) the OUTLET SHUTOFF valve (7) sufficiently to relieve
the high pressure down to 500 psig on the OUTLET PRESSURE gage (6). Close the OUTLET
SHUTOFF valve (7) and OUTLET BLEED valve (4) fully counterclockwise.
(11) Remove the inlet hose from the inlet connector.
(12) Remove tape from safety switch.
(13) Replace housing enclosure, figure 3-4, (3) by placing enclosure over assembly and
reinstalling the safety switch (16) on rear of enclosure. Install the 18 retaining screws (1) in lower end
of enclosure and 14 screws (2) in the front panel assembly.