29. Cut connector (Figure 65, Item 5) and strip 1/4 in. insulation from two light wires (Figure 65, Item 1).
30. Insert two light wires (Figure 65, Item 1) into solderless connectors (Figure 65, Item 4) at end of light extension
wires (Figure 65, Item 2), and crimp securely.
31. Apply heat to two shrink wrap tubes (Figure 65, Item 3) until shrink wrap tightly encloses connectors.