0052-57
Change 1
TB 9-3950-253-13&P
0052
LIGHT BAR ASSEMBLY INSTALLATION – CONTINUED
NOTE
Ground wire is on PLS only.
4. At inside light location of bracket (Figure 58, Item 1), feed light wire (Figure 58, Item 5) through bracket and
connect to original wiring harness connector (Figure 58, Item 4).
5. Install light (Figure 58, Item 7), two screws (Figure 58, Item 2), ground wire (Figure 58, Item 3) and two nuts
(Figure 58, Item 6) on bracket (Figure 58, Item 1).
Figure 58.
Inside Light Installation.
052
6. At outside light location of bracket (Figure 59, Item 1), feed light wire (Figure 59, Item 6) through bracket and
connect to original wiring harness connector (Figure 59, Item 5).
7. Feed ground wire (Figure 59, Item 4) from harness (Figure 59, Item 7) through back of bracket (Figure 59,
Item 1) and back of light (Figure 59, Item 10), out through access hole (Figure 59, Item 9).
8. Install light (Figure 59, Item 10), two screws (Figure 59, Item 2), ground wires (Figure 59, Items 3 and 4), and
nuts (Figure 59, Item 8) on light bracket (Figure 59, Item 1).
9. Paint exposed metal surfaces.
Figure 59.
Outside Light Installation.
052
1
2
3
2
4
5
5
6
6
7
1
2
3
4
2
10
9 (HIDDEN)
8
1
8
7
6
5
4


Back to Top