LIGHT BAR ASSEMBLY INSTALLATION
00052
1. Place original wiring harness (Figure 56, Item 1), left light bracket (Figure 56, Item 4) and right light bracket
(Figure 56, Item 3) on flat work surface.
2. Place tab (
Figure 56
, Item 2) at outer end of original wiring harness (
Figure 56
, Item 1) as shown.
Figure 56.
Light Brackets and Original Harness.
052
NOTE
Perform steps 4 through 7 for both left and right side brackets.
3. On both sides of bracket (Figure 57, Item 1) scrape or grind away paint surrounding ground mounting holes
(Figure 57, Item 2).
Figure 57.
Grind Paint from Grounding Holes.
052
2
3
4
3
1
2
2
2
1