INSTALLATION - Continued
21.
Connect two vent lines (Figure 14, Item 14) to elbows (Figure 14, Item 13).
22.
Connect interlock vent line (Figure 14, Item 11) to elbow (Figure 14, Item 12) and elbow (Figure 14, Item 10).
23.
Connect supply line (Figure 14, Item 5) to interlock valve elbow (Figure 14, Item 4).
24.
Connect supply line (Figure 14, Item 2) to interlock air cylinder elbow (Figure 14, Item 3) and interlock valve
elbow (Figure 14, Item 1).
25.
Connect supply line (Figure 14, Item 7) to air cylinder elbow (Figure 14, Item 6).
26.
Correct interlock valve lead (Figure 14, Item 9) to connector (Figure 14, Item 8).
M9896DAA
13
14
11
12
13
14
4
5
6
7
10
9
8
11
1
2
3
Figure 14.
Transfer Case Lines and Cables Installation.
TM 9-2320-272-23-3
0386
0386-19