INSTALLATION - Continued
37.
Install propeller shaft (Figure 19, Item 2) on PRO flange (Figure 19, Item 1) with four screws
(Figure
19,
Item
3), lockwashers (Figure 19, Item 5), and locknuts (Figure 19, Item 4). Tighten locknuts
32
to
40
lb-ft (43 to 54 N·m).
4
M7075-1DAA
5
1
2
3
Figure 19.
Transfer Case Power Takeoff Installation.
END OF TASK
FOLLOW-ON MAINTENANCE
1.
Install transfer case shift rod. (WP
0396)
2.
Install transfer case front axle engagement control valve. (WP
0388)
3.
Check parking brake adjustment. (WP
0432)
4.
Installation transmission to transfer propeller shaft. (WP
0403)
5.
Install transfer case to forward rear axle propeller shaft. (WP
0402)
6.
Fill transfer case to proper oil level. (Volume 5, WP
0820)
END OF TASK
END OF WORK PACKAGE
TM 9-2320-272-23-3
0386
0386-24