INSTALLATION
Install shift lever shift rod (Figure 4, Item 3) on shift lever (Figure 4, Item 1) and cross shaft lever
(Figure
4,
Item
5) with two pins (Figure 4, Item 2) and cotter pins (Figure 4, Item 6) installed through clevises
(Figure 4, Item 4).
6
2
4
6
9-5/8 IN. (24.4 CM)
M7050DAA
2
4
3
5
1
Figure 4.
Transfer Case Shift Lever Shift Rod Installation.