OPERATOR MAINTENANCE
TRACK INSTALLATION
INITIAL SETUP:
Tools and Special Tools
General mechanic's tool kit
(WP 0135, Table 1, Item 2)
Double-face blacksmith sledge hammer
(WP 0132, Table 2, Item 30)
Fibrous rope (WP 0132, Table 2, Item 49)
Socket wrench set (WP 0132, Table 2, Item 86)
Tanker bar (crowbar pinch, 5 ft)
(WP 0132, Table 2, Item 12)
Personnel Required
Crewman (3)
References
Chocking vehicle (WP 0103)
References (cont.)
Driving the vehicle (WP 0014)
Shut down main engine (WP 0017)
Starting main engine (WP 0010)
Stopping the vehicle (WP 0015)
Track disconnect and connect (WP 0106)
Transmission shift selection (WP 0012)
Equipment Condition
Vehicle chocked (WP 0103)
TRACK INSTALLATION
NOTE
Retain lockwashers for installation. Notify maintenance to replace lockwashers when
mission permits.
1.
Remove two screws (Figure 1, Item 3) and two lockwashers (Figure 1, Item 2) from rear fender
(Figure 1, Item 1) of track being installed.
Figure 1.
Rear Fender.
TM 9-2350-256-10
0114
0114-1