INSTALLATION
1.
Install four grommets (Figure 2, Item 14) and two grommets (Figure 2, Item 8) on battery box
(Figure
2,
Item
6).
2.
Align vent tube (Figure 2, Item 9) with hole in cab floor (Figure 2, Item 10) and install battery box
(Figure
2,
Item
6) on cab (Figure 2, Item 11) with cable grommets (Figure 2, Item 8) aligned with cables
(Figure 2, Item 7).
3.
Pull battery cables (Figure 2, Item 7) through grommets (Figure 2, Item 8).
4.
Secure battery box (Figure 2, Item 6) to cab (Figure 2, Item 11) with four lockwashers (Figure 2, Item 4) and
screws (Figure 2, Item 3). Tighten screws to 25 lb-ft (34 N·m).
5.
Place wood battery support blocks (Figure 2, Item 1) in battery box (Figure 2, Item 6).
6.
Install hose (Figure 2, Item 2) on battery box (Figure 2, Item 6) and cab (Figure 2, Item 11) with two clamps
(Figure 2, Item 5).
7.
Pull slave receptacle cables (Figure 2, Items 12 and 13) through grommets (Figure 2, Item 14).
M8040DAA
1
2
3
4
5
6
7
8
9
10
11
12
13
14
5
Figure 2.
Battery Box Installation.
END OF TASK
TM 9-2320-272-23-2
0347
0347-3