TM-9-2320-272-23-4

TRUCK, 5-TON, 6X6, M939, M939A1, AND M939A2 SERIES TRUCKS (DIESEL)

TECHNICAL MANUAL; FIELD MAINTENANCE MANUAL; VOLUME 4 OF 5

SEPTEMBER 2012

  TM-9-2320-272-23-4 - Page 512 of 1393

INSTALLATION - Continued
2.
Install left 3-phase receptacle wiring harness (Figure 17, Item 8) and three wires (Figure 17, Item 6) in load
center (Figure 17, Item 3) and on triple circuit breaker (Figure 17, Item 4) with three screws
(Figure
17,
Item
5).
3.
Install wire (Figure 17, Item 1) on neutral buss bar (Figure 17, Item 2) with screw (Figure 17, Item 7).
M3066DAA
2
3
4
5
6
7
8
1
Figure 17.
Load Center Box.