INSTALLATION - Continued
9.
Install three wires (Figure 20, Item 6) and entrance receptacle harness (Figure 20, Item 8) on circuit breakers
(Figure 20, Item 4) in load center (Figure 20, Item 3) with three screws (Figure 20, Item 5).
10.
Install wire (Figure 20, Item 1) on neutral buss bar (Figure 20, Item 2) with screw (Figure 20, Item 7).
M10296DAA
4
5
6
3
2
7
8
1
Figure 20.
Load Center Box.
TM 9-2320-272-23-4
0639
0639-24