FIELD MAINTENANCE
CHASSIS WIRING HARNESS REPLACEMENT
INITIAL SETUP:
Tools and Special Tools
Tool Kit, General Mechanic's
(WP
0115, Table 1, Item 1)
Materials/Parts
Fifteen lockwashers
(WP
0085, Figure 4, Item 2)
Two electrical tiedown straps
Materials/Parts (cont.)
(WP
0085, Figure 4, Item 5)
Lockwasher (WP
0085, Figure 4, Item 8)
Tag, marker (as needed)
(WP
0114, Table 1, Item 27)
Equipment Condition
Intervehicular cable disconnected from
prime mover (WP
0005)
NOTE
Configuration of chassis wiring harness varies slightly with model. The M116A2 chassis trailer
is shown.
REMOVAL
1.
Remove four screws (Figure 1, Item 2), lockwashers (Figure 1, Item 1), and cover (Figure 1, Item 5) from
junction box (Figure 1, Item 3) at roadside drawbar (Figure 1, Item 4). Discard lockwashers (Figure 1, Item 1).
1
2
3
4
5
M116_M101_062
Figure 1.
Junction Box Cover Removal.