STACKING - Continued
WARNING
Trailer stacking procedure must be done with both trailers on a level, stable surface. Failure
to comply may result in injury or death to personnel.
NOTE
•
Right and left safety chains are removed the same way, left side shown.
•
Steps (1) through (4) are for the trailer that will be on top. Steps (5) through (8) are
for the trailer that will be on the bottom.
•
Locknuts removed in Step (1) are reused in Step (3).
1.
Remove screw (Figure 1, Item 6), locknut (Figure 1, Item 2), and link coupling (Figure 1, Item 5) from plate
(Figure 1, Item 1).
2
3
4
5
6
1
Figure 1.
Trailer Stacking for Air, Sea, or Rail Transport.
2.
Remove safety chain (Figure 1, Item 4) from link coupling (Figure 1, Item 5) and hook (Figure 1, Item 3).
3.
Install link coupling (Figure 1, Item 5) on plate (Figure 1, Item 1) with screw (Figure 1, Item 6) and locknut
(Figure 1, Item 2).
4.
Repeat Steps (1) through (3) for right side.
5.
Remove safety chains from bottom trailer (WP
0114).
6.
Install link coupling (Figure 2, Item 3) on plate (Figure 2, Item 1) with screw (Figure 2, Item 4) and locknut
(Figure 2, Item 2).
TM 9-2330-342-23&P
0125
0125-2