STARTER REPLACEMENT (Sheet 7 of 7)
11. Using screwdriver, secure small cable (P) onto
bottom front of solenoid relay with screw and new
external tooth lockwasher (Q).
12. Install heavy cables (R) and (S) and tagged light
cable (T) onto lower terminal of tarter switch relay
solenoid (U).
Using 3/4 inch socket and torque
wrench, secure cables with nut and lockwasher (V)
to 168-192 lb-in (19-22 N
•
m).
13. Install two double-braided ground straps (H) and two
heavy cables (X) and (Y) and tagged light cable (Z)
onto large terminal at starter motor (AA).
Using 3/4
inch socket and torque wrench, secure cables with
nut and lockwashers to 168-192 lb-in (19-22 N
•
m).
14. Install starter low voltage relay solenoid (page 10-37) (2D engine only).
15. Connect powerplant for gound hop (page 5-54).
16. Start engine (TM 9-2350-260-10).
17. Stop engine (TM 9-2350-260-10).
18. Using pliers, secure four bracket bolts with lockwire
(Item 59, Appendix D) (AB), exactly as shown in the
figure, to prevent them from loosening.
19. Coat all exposed terminal fittings with glyptol
(Item 38, Appendix D).
20. Disconnect ground hop kit (page 5-67).
21. Install 2A powerplant (page 5-14) or 2D powerplant
(page 5-40).
End of Task