5-13
TB 9-2320-387-35-4
Section VII. INTEGRATED RACK INSTALLATION
NOTE
Perform steps 7-1 and 7-2 if blast shield is installed. Perform
steps 7-3 and 7-4 if blast shield is not installed.
7-1.
Using rack support (1) as template, locate, mark, and drill three 0.375-in. diameter holes (3) in
blast shield (4) and through tunnel (5).
7-2.
Install three inserts (2) in holes (3) in blast shield (4).
7-3.
Using rack support (1) as template, locate, mark, and drill three 0.375-in. diameter holes (3) in
tunnel (5).
7-4.
Install three inserts (2) in holes (3) in tunnel (5).
Figure 5-17.
Figure 5-18.
1
2
4
5
3
1. RACK SUPPORT – 889509-22 – QTY. 1
2. INSERT – ALS4-616-150 – QTY. 3
~
~
1
2
3
5