REPLACE TRANSMISSION TO DIFFERENTIAL SHAFT — Continued
0347 00
4.
TIGHTEN SCREWS TO 86 TO 94 LB-FT (117-128 N·M) TORQUE. Use torque wrench and adapter. Loosen and
retighten to correct torque. See WP 0120 00 for torque wrench reading with adapter.
FOLLOW-THROUGH STEPS
1.
Close power plant front access door (see your -10).
2.
Raisetrimvane(seeyour-10)
.
3.
Road test carrier (WP 0120 00) to check transmission-to-differential shaft.
4.
Stop/shutdown engine (see your -10).
END OF TASK