TM 9-2350-261-20-2
REPLACE UPPER ACCELERATOR LINKAGE — Continued
0399 00
5.
Install pin (1) and washer (20) on bracket assembly (2). Secure with new cotter pin (3).
6.
Install tee (4) on bracket assembly (2). Secure with nut (5) and washer (6).
7.
Connect fuel line (7) to tee (4).
8.
Install throttle link (8) on bracket assembly (2). Secure with new locknut (9) and screw (10).
9.
Install spring (11) and washer (12) on throttle link (13). Insert throttle link through pin (1) and secure with new cotter
pin (14).
10. Install governor throttle arm (15) on governor (16). Tighten screw (17).
11. Install throttle link (13) on governor throttle arm (15). Secure with screw (18) and new locknut (19).
12. Adjust accelerator and transmission throttle valve linkage (WP 0401 00).
FOLLOW-THROUGH STEPS
WARNING
Wearing loose clothing around moving parts can allow personnel to get caught and cause injury
or death. Tuck in loose clothing.
1.
Start engine (see your -10). Check that upper accelerator linkage operates properly. Stop/shutdown engine (see your -10).
2.
Install power plant rear access panel (WP 0431 00, WP 0432 00, or WP 0433 00).
3.
Raise and lock ramp (see your -10).
4.
Stop/shutdown engine (see your -10).
END OF TASK
0399 00-4