MWO-5-2350-262-35-2

ARMORED COMBAT EARTHMOVER (ACE), M9

MODIFICATION WORK ORDER

  MWO-5-2350-262-35-2 - Page 4 of 33

MWO 5-2350-262-35-2
1-2
NOTE
Total hours to perform one CCS installation of this MWO is 6 hours.
Total hours to perform one MCS removal and one CCS and NBC system installation of this MWO is 16 hours.
d. MWOs to be applied prior to or concurrently with the application of this MWO:
Not applicable.
e.
Additional information deemed necessary to assist in the application of this MWO:
PUBLICATIONS:
AR 750-10
TM 750-245-4
DA Pam 738-751
DA Pam 738-750
TB 43-0209
1-7
TECHNICAL PUBLICATIONS AFFECTED/CHANGED.
PUBLICATIONS:
TM 5-2350-262-20-1, dated January 1997, with Change 3, dated March 2000
TM 5-2350-262-20-2, dated January 1997, with Change 3, dated March 2000
TM 5-2350-262-24P, dated March 2000
TM 5-2350-262-34, dated January 1997, with Change 2, dated March 2000
1-8
MWO KITS/PARTS AND THEIR DISPOSITION.
a.
See applicable chapter for parts.
b.
Bulk and Expendable Material are as follows:
Part No.
CAGE
NSN
Description
Qty
4700
38921
Charge/Purge Kit – MCU
Cooling
A/R
MIL-P-83800
81349
Propylene Glycol, Gallon
A/R
c.
Return removed (no longer required) parts to unit for disposition.
1-9
SPECIAL TOOLS; TOOL KITS; JIGS; TEST, MEASUREMENT, AND DIAGNOSTIC
EQUIPMENT (TMDE); AND FIXTURES REQUIRED.
See applicable chapter for tools/kits.
1-10 MODIFICATION PROCEDURES.
See applicable chapter for modification procedures.
1-11 CALIBRATION REQUIREMENTS.
Not applicable.
1-12
WEIGHT AND BALANCE DATA.
Weight and balance are not significantly affected.