MWO 5--2350--262--35--4
5--9
SECTION II INSTALLATION AND PRELIMINARY ROUTING OF HDC CABLE
ASSEMBLIES -- CONTINUED
NOTE
Step u below applies to Figure 5--5.
u.
Allow lower cable assembly W3 (1) to hang down along left side of bowl area below DCV bank and
primary manifold assembly, down near left main manifold assembly to underside of vehicle, as shown in
Figure 5--5.
Figure 5--5. Initial Placement of Lower Cable Assembly W3
NOTE
Lower cable assembly W3 electrical connections are not made at this time. Lower cable
assembly W3 electrical connections to HDC solenoid valves and pressure transducers
are performed in Section VI.