47.
Connect tubes (figure 60, items 3 and 4) to adapter (figure 60, item 1) and elbow (figure 60, item 2)
located at front end of primary reservoir (figure 60, item 5).
Figure 60. Connecting Tubes to Primary Reservoir.
NOTE
The 3/8 in. (9.5 mm) green tubing between the double check valve
and the tee on the double check valve stop/light switch is replace
with 1/2 in. (13 mm) green tubing.
48.
Remove tube (figure 61, item 8) from elbows (figure 61, items 1 and 6), elbow (figure 61, item 6) from
double check valve (figure 61, item 5), and elbow (figure 61, item 1) from tee (figure 61, item 3) at
double check valve/stoplight switch (figure 61, item 4). Discard tube (figure 61, item 8).
49.
Install new adapter (figure 61, item 7) on double check valve (figure 61, item 5), and install new adapter
(figure 61, item 2) on tee (figure 61, item 3) at double check valve/stoplight switch
(figure 61, item 4).
50.
Cut and install new piece of 1/2 in. (13 mm) green tubing (figure 61, item 8) on adapters
(figure 61, items 2 and 7).
Figure 61. Replacing Tube Between Double Check and Quick Release Valves.