INSTALLATION OF ABS AIR LINES – CONTINUED
40.
Remove hex-head plug (figure 58, item 13) from double check valve (figure 58, item 3), and install
socket-head plug (figure 58, item 7) on double check valve (figure 58, item 3) in its place.
41.
Install new elbow (figure 58, item 8) on brake treadle valve (figure 58, item 6), rotate double check
valve (figure 58, item 3) 1/4 turn clockwise, and connect tubes (figure 58, items 5, 14, 17, and 18) to
elbows (figure 58, items 2, 4, and 15) and adapter (figure 58, item 16).
42.
Cut and route new 168 in. (427 cm) 5/8 in. (16 mm) green tubing (figure 58, item 9) under truck cab up
to location at brake treadle valve (figure 58, item 6), and connect end of tube (figure 58, item 9) to
elbow (figure 58, item 8) on brake treadle valve (figure 58, item 6).
Figure 58. Installing 5/8 Tube on Brake Treadle Valve.